Aerial view of the Junik project site
Junik landscape, western Kosovo
Helios Power sh.p.k. · Kosovo

Solar power
for Kosovo

We develop Junik Solar Park A & B: a 100 MWp ground-mounted photovoltaic park in western Kosovo, built to feed around 145 GWh of clean electricity a year into the 220 kV grid.

Scroll
0 MWp
Installed Capacity
0 GWh
Energy per Year
0 ha
Land Secured
0 kV
Grid Connection
Junik project site from the air
100 MWp Junik Solar Park

A Kosovo developer of utility-scale solar

Helios Power sh.p.k. was founded in Deçan in 2021 to develop renewable energy projects in Kosovo. Our flagship is Junik Solar Park A & B: 100 MWp of photovoltaic capacity on 85 hectares of leased land in the Municipality of Junik, with its own substation and a connection to the national 220 kV transmission grid.

100 MWp Solar Park

135,268 bifacial 740 Wp modules on fixed ground-mounted tables

85.3 ha of Land

Eight cadastral parcels in Junik, with asphalt road access on all sides

Own 35/220 kV Substation

Two 80 MVA transformers stepping the park up to transmission voltage

220 kV Grid Link

About 8 km of new line into the KOSTT Prizren 2 – Fierzë circuit

The Junik Site
From Above

Drone footage of the project area in Junik, at the foot of the mountains in western Kosovo.

100 MWp on the
Junik plain

At 482 m altitude and 42.46° N, Junik receives strong, steady sunlight. The energy yield below comes from the project’s PVsyst simulation (June 2025) and its feasibility and ESIA study (October 2024).

Rows of ground-mounted solar modules (reference photo)
Technical Design · reference photo

The Installation

135,268 bifacial 740 Wp modules on 19,324 fixed tables facing south at 25°, feeding 287 string inverters. Module rows sit about 4 m apart. The park is planned to reach commercial operation within 12 months of the start of construction.

100
MWp DC
135K
Modules
287
Inverters
Large solar park in a hilly landscape (reference photo)
Energy & Impact · reference photo

Yield and CO₂

Kosovo’s grid runs mostly on lignite, at about 1,220 g of CO₂ per kWh. Replacing that power with solar from Junik avoids around 4.4 million tonnes of CO₂ over the park’s 30-year life, after counting the emissions of building it.

1,450
kWh / kWp / yr
88%
Performance Ratio
4.4 Mt
CO₂ Avoided, 30 yrs
145
GWh per year
Expected Annual Production

The simulation gives 145,004 MWh delivered to the grid in an average year, from 100 MWp of modules and 100.5 MWac of inverter capacity.

High-voltage transformer in a substation (reference photo)

100 MW to the 220 kV grid

KOSTT has granted Junik Solar Park an export capacity of 100 MW. The park steps its power up in its own substation and joins the national transmission line between Prizren 2 and Fierzë.

35/220 kV Substation

Two 80 MVA transformers, four 220 kV bays and fourteen 35 kV cells.

8 km, 220 kV Line

A new double-circuit overhead line, looped in and out of the Prizren 2 – Fierzë circuit.

Handed to KOSTT

Once built, the connection assets pass to KOSTT, the transmission system operator.

From company to ready-to-build

  1. 2021

    Helios Power sh.p.k. founded

    Registered with ARBK in Deçan on 7 September 2021 to develop photovoltaic projects in Kosovo.

  2. 2022

    Grid connection consent

    KOSTT, Kosovo’s transmission system operator, first consents to two connections of 50 MW each (50 + 50) at the 220 kV Prizren 2 – Fierzë line (technical information no. 1907, 20 September 2022).

  3. Oct 2024

    Feasibility and ESIA study

    Feasibility and environmental and social impact study for the 100 MWp bifacial PV park, Junik A & B.

  4. Jun 2025

    Energy yield simulation

    PVsyst simulation confirms 145 GWh a year at a performance ratio of 88%.

  5. Aug 2025

    Building conditions issued

    The Ministry of Environment, Spatial Planning and Infrastructure approves the building conditions for Junik Solar Park A+B, 100 MW, on 4 August 2025. They are valid for 24 months.

  6. Today

    One 100 MW connection

    KOSTT changes the approval from two 50 MW connections to a single 100 MW connection for the whole park.

  7. Next

    Construction and operation

    EPC contract, the 35/220 kV substation and the 8 km line, then commissioning within about 12 months of construction start.

Solar parcel and 39 residential plots

Next to the solar park, a second site in the Junik cadastral zone is planned as a mixed development: a 15.22 ha parcel for solar panels, a 5,000 m² transformer station and 39 residential plots along a new 10 m road.

Most residential plots are 400–456 m², with one restaurant parcel by the lake. The site plans below show the whole development with and without the orthophoto.

Modern Eco Villa 39 Plots

Residential Plots

Plots for private homes with mountain views, next to their own source of solar electricity.

Villa Parcels View 15.22 ha

Solar Parcel

A 15.22 ha solar parcel with its own 5,000 m² transformer station plot.

Lake at the Junik development site

Lake and restaurant parcel

The development site includes a natural lake. One parcel next to it is set aside for a restaurant that will serve residents and visitors.

Natural Lake

The lake stays as the centre of the site, with the plots laid out around it.

Restaurant Parcel

One dedicated parcel on the lakeside for a restaurant.

Community Hub

A meeting place for residents and visitors to the Junik site.

Site Plans

Site plans of the Junik development, Junik cadastral zone, with and without the orthophoto.

Permits, studies and designs

Junik Solar Park is backed by 32 documents from Kosovo’s ministries, the Municipality of Junik, KOSTT and independent engineers. Open any document to see a preview of its first page. Full copies are shared with investors and partners on request.

Why the Junik project works

The figures come from the project’s own studies, not from estimates.

Strong Sun

1,450 kWh per kWp per year on fixed south-facing tables, simulated with Meteonorm data for Junik.

Grid Ready

Own 35/220 kV substation and a short 8 km line to the transmission grid.

Permitted

Environmental impact assessment completed and building conditions issued by the Ministry.

Cleaner Grid

About 4.4 million tonnes of CO₂ avoided over 30 years in a lignite-heavy system.

Talk to Helios Power

For investment, partnership, offtake or plot enquiries about the Junik projects, send us a message and we will reply with the project documentation.

or write to info@heliospower.solar